Current Projects
Project Start Date Expected Completion
Clarendon Hotel Phase II November 2008
Sewer Lining
Upcoming Projects
Project Estimated Start Date Estimated Completion Date
National Road Bikeway Bridge April, 2009 Unknown
National Road Bikeway Tunnel February, 2009 June, 2009
St. Clairsville Community Garden March 1, 2009 Unknown
Fairgrounds

back to top

Completed Projects
Project Start Date Completion Date
Water Tank Painting August, 2008 October, 2008
Bett-Mar Street Replacement
East End Street Project 2008 December, 2008
Electric Substation
Communities In Bloom Spring, 2008 July, 2008

back to top

CURRENT PROJECTS

  • Clarendon Hotel - Phase II

    The Clarendon Hotel was constructed in 1890 with 38 rooms available to travelers along the National Road. In 2001, after years of the structural decline, the City purchased the building with the intent of restoring, rehabilitating and eventually finding a tenant. Phase I of this project is complete. Phase I included the entire cleaning and tuck pointing of the exterior of the structure, restoration and replacement of the windows, interior structural work and roof work.

    November 2008 saw the start of Phase II of this project. Phase II includes some interior demolition, the construction of an elevator shaft and the installation of a fire-rated stairwell in the interior of the hotel. These improvements are necessary to bring the building up to current Ohio Building Code standards. The City envisions that the final phase will include the completion of the interior of the Clarendon Hotel and occupancy by a tenant or tenants. Stanley Miller Construction is the contractor on Phase II of this project.

    Stanley Miller Construction began work on Phase II of the hotel project in November 2008 and should finish work by February 2009. Phase II consists of the installation of a fire-rated stairwell inside the building and the construction of an elevator shaft. The elevator cab will be installed as part of Phase II. Regardless of future use, these improvements are necessary to bring the building up to current Ohio Building Code

  • Sewer Lining

back to top

UPCOMING PROJECTS

The National Road Bikeway in St. Clairsville opened for public use on June 26, 1998. It has since become one of the most successful projects in the City and is heavily used by residents and non-residents alike. Two of the more interesting features on the bikeway, the tunnel and the bridge are in line for substantial repairs.

  • National Road Bikeway Bridge

    The bridge is a 522 foot long steel truss bridge and is in need of some repairs. Rehabilitation will include replacing structural steel, concrete repair to the north abutment wall, sandblasting of the bridge and painting. The contract for the proposed work to be undertaken has been awarded and is tentatively scheduled to begin in April 2009. While work is underway, the bikeway will be closed from Pecks Lane to North Market Street.

  • National Road Bikeway Tunnel

    The tunnel found on the bikeway is 532 feet long with an interior that is 40 feet high at some points. Rehabilitation of the tunnel is planned to commence in February 2009 and be completed in May 2009. A protective fence will be added to the southern wing walls, new under drains and catch basins will be installed the length of the tunnel and existing weep pipes will be connected into the under drains instead of draining on the asphalt. Large sections of the interior walls of the tunnel will be removed where needed and replaced with the new mortar. Much of this work is being undertaken to assist in the diversion of water infiltration. The tunnel will not be open to the public while work is underway. The bikeway will be closed from the south side of the tunnel to Station Street during construction.

  • St. Clairsville Community Garden

    Plans are being finalized for the construction of a community garden north of St. Clair Avenue, just east of South Sugar Street. For a small deposit, residents and non-residents will be able to plant a garden on a level, easily accessible plot. Starting March 1, 2009 plots will be assigned on a first come first serve basis. Plot maps should be available by February 1.

back to top

COMPLETED PROJECTS

  • Water Tank Painting
  • Bett-Mar
  • East End Project
  • Substation
  • Communities In Bloom

back to top